Lancaster & Carlisle Line Bridge Number 169, River Eamont

Scour Protection Works

In the early hours of Monday 19th October 1987, the Afon Tywi between Llandovery and Llandeilo, swollen by earlier rainfall, removed an excess of bed material from the base of the bridge carrying the Central Wales Line at Glanrhyd. The resulting pier collapse dragged down the steel deck that it carried. Tragically, this problem was not identified by British Rail staff until the next Sprinter plunged into the river drowning several passengers.

Up until the Glanrhyd failure, the accepted examining procedure was to carry out a special inspection of structures after heavy rain if scour was suspected. Scour however can occur suddenly, making post-flood examination pointless. Following the collapse, BR and Hydraulics Research carried out a comprehensive study that resulted in the production of Handbook 47, the manual for assessment of scour risk. Some 2200 railway bridges over water initially appeared vulnerable to scour. Handbook 47 considers various factors besides the bridge and immediate vicinity, such as river and landscape characteristics and therefore the number of bridges considered to be at risk was reduced to 350 following revised assessment. The nature of the assessment also prioritised risk, thus aiding the budgeting of scour protection works.

 

Bridge 169 carries the Lancaster and Carlisle Line over the River Eamont just south of Penrith, Figure 1. Following Glanrhyd, this bridge was assessed under Handbook 47 and was considered to be at risk from scour, justifying additional protection works.

The viaduct consist of six masonry arches, Figures 2, 3 and 4, of which only one is a permanent river channel.

Figure 1 - Location plan

 

Figure 2 - East elevation drawing

 

Figure 3 - West elevation

 

Figure 4 - West elevation of river channel

During flood events the ground beneath the adjacent arches is also flooded. In the past 20 years, various scour protection works had been carried out at the foot of the river channel piers. Primarily, a 750mm wide construction of concrete filled hessian bags had been constructed, topped with a concrete apron. Over time however, this apron itself had been scoured, leaving the base of the piers exposed to potential scour, Figure 5.

 

Works in rivers require the approval of the Environment Agency who have a statutory responsibility to protect watercourses. In particular this would entail ensuring that the river regime was not altered and that pollution was prevented. At Br 169 avoidance of alteration to the regime was relevant to the protection of the bridge as much as of the natural environment.

Figure 5 - North pier prior to works

Even slight alterations to the river flow by civil engineering work could result in change in the hydraulics of the river, thus worsening scour potential. Furthermore, the Environment Agency had particular concern that a fish farm down stream from the works was not adversely affected by disturbance of sediment or contamination of the river by cementitious products.

Although not at risk from the actual works in the river, concern was expressed by one landowner adjacent to the bridge. Unlike farmers who constitute most neighbours of the railway, this gentleman farmer, and this term should be taken literally, to the north-east of the bridge, was a tree collector who travelled the world in search of specimens. Walking down from the ancestral pile to the river, he proudly pointed out his most recent specimen, which he had recently brought over from Chile. This arboretum next to Bridge 169 must represent one of the most unusual woods bordering the railway.

In order to satisfy the submission requirements for works in rivers, a scheme drawing was required that would illustrate the proposals include the existing and proposed river profile at the bridge. A physical survey of the river in the vicinity of the bridge was therefore carried out using a bank based survey instrument and dinghy and from this a drawing could be produced. The proposed works must be shown not to significantly change bed and bank profiles. I had some fun paddling the inflatable dinghy during the survey, Figure 6, and I didn't get wet either!

Figure 6 - Survey using an inflatable dinghy

Figure 7 - Drawing section

The proposed works had to be more resistant to scour and the resulting scheme entailed provision of rock armour around the foot of a reconstructed apron, Figure 7. Although a suitable time of year is always aimed for, some amount of water must still be expected, with method and materials being appropriately chosen.

Initially a trench nominally 1.5m wide was excavated around the remains of the aprons, returning half way along the end faces of the piers to a depth of 1m below the level of general scour. This empirical depth assumes that providing the river regime is not altered, scour will not undermine the finished works.

Following this, loose bagwork was removed from the dilapidated apron and where the voids were large enough, they were filled with new hessian bags containing 1:2:4 cement: sand: aggregate mix.

It was anticipated that hessian would retain the majority of the cement matrix prior to curing.

Where necessary, new sections of apron were built up from the solid base of the excavation in bagwork. Following reconstruction of the bagwork core, shuttering was constructed around the apron and all voids grouted with a Pozament PFA grout, Figure 8.

Figure 8 - Shuttering around south pier

The completed works, Figures 9 &10, are a significant improvement on the scour protection previously provided as the new aprons are now fronted by armourstone blocks, set below the existing local scour level at the piers. Ongoing regular programmed bridge examinations and high water flow checks will ensure that the scour protection is not compromised. In addition to this, automatic scour monitoring devices such as sonar, radar, video and special sensors have been considered and will without doubt play an increasingly important role in the future.

Figure 9 - North pier after works

 

Figure 10 - Finished scour protection works